Skip to content
CityAM
Main navigation
  • News
    • News
      • Latest Business News
      • Economics
      • Politics
      • Tech
      • Banking
      • FTSE 100 Live
      • Retail
      • Insurance
      • Legal
      • Property
      • Transport
      • Markets
    • From our partners
      • AON
      • Bayes Business School
      • Canada BIDs
      • Central London Alliance CIC
      • Destination City
      • Halkin
      • Olympia
      • Inside Saudi
      • Tottenham Hotspur Stadium
      • Santander X
      • YEAR SIX Dividend
    • Featured

      Ministers open door to phased Heathrow third runway plan

      Heathrow Airport terminal bustling with travelers and staff, showcasing modern architecture and international flight activity

      Submit a story

      Tell us your story.

      Submit
  • Opinion
  • Sport
    • Latest Sports News
      • Sport
      • Sport Business
    • From our partners
      • The Morning Briefing: SBS x CityAM
      • Aramco Team Series
      • LIV Golf
    • Featured

      Concern as gambling black market set for £40m Royal Ascot boost

      GettyImages 2282074836 showing a significant event with key figures in a professional setting, highlighting a major develo...

      Submit a story

      Tell us your story.

      Submit
  • Life&Style
    • Life&Style
      • Life&Style
      • Toast the City Awards
      • The Magazine
      • Travel
      • Culture
      • Motoring
      • Wellness
      • The RED BULLETiN
      • Do it with Shared Ownership
      • Media Speak Hub
    • Featured

      Mexican Michelin stars arrive in the Square Mile at Ned pop-up

      The Ned Los Felix Mexican restaurant interior with vibrant decor and patrons enjoying authentic Mexican cuisine

      Submit a story

      Tell us your story.

      Submit
  • Investec
  • Events
  • Latest Paper
Wednesday 24 January 2024 10:47 am

Hinkley Point C faces additional four-year multi-billion pound delay

By: Rhodri Morgan

Add as a preferred source on Google
Both Hinkley Point C and Sizewell C nuclear power stations are mired in delays or pre-construction barriers.
Both Hinkley Point C and Sizewell C nuclear power stations are mired in delays or pre-construction barriers.

Completion of the Hinkley Point C nuclear power plant has been delayed by up to four more years at the cost of billions of pounds, according to its manufacturers.

France’s state energy company EDF, which operates all of the UK’s five active nuclear power stations, said the project’s launch date has been pushed from June 2027.

Three different scenarios forecast by the company see the reactors not coming online until 2029, 2030 or 2031 in the worst possible scenario.

Additionally, the project’s bill is set to run up to around £46bn when adjusted for inflation on the 2015 estimates of £31-34bn.

This marks more than double the initial budget of £18bn for a plant that was scoped to come online in 2017.

In December, EDF’s partner in the project, China General Nuclear (CGN), had halted funding for the site after the uk government took over CGN’s stake in Hinkley’s proposed sister site, Sizewell C in Suffolk.

In a note to Hinkley project staff, Stuart Crooks, managing director of Hinkley Point C, said: “Like other infrastructure projects, we have found civil construction slower than we hoped and faced inflation, labour and material shortages – on top of COVID and Brexit disruption.”

Though the government’s nuclear roadmap was released last week, the sector seems to remain absent of the positive forward momentum it has been crying out for.

Nearly all existing stock is set to come offline by 2030, Sizewell C remains in the pre-construction phase and the government has outlined plans for a new major reactor that might not be switched on for over a decade.

Read more

X-energy Submits Xe-100 HTGR for UK Generic Design Assessment

Share this article

  • Facebook
  • X
  • LinkedIn
  • WhatsApp
  • Email

Similarly tagged content:

Sections

  • News

Categories

  • Energy

Trending Articles

  • More Big Four blues as Deloitte plans to slash UK audit roles

  • Rathbones to suspend thousands of client account inflows after FCA probe deals £530m blow

  • As it happened: Stocks sink after Fed and Bank of England opt for hawkish hold; Oil price tumbles

  • Rolls-Royce shares surge as SMR unit bags multi-billion pound Swedish nuclear contract

  • Baillie Gifford in line for Anthropic windfall just months after £3.6bn SpaceX bonanza

More from CityAM

  • X-energy Submits Xe-100 HTGR for UK Generic Design Assessment

    Business Wire
  • Type One Energy, Tokamak Energy, and AECOM Form the UK Infinity Fusion Consortium to Accelerate Development of a Commercial Fusion Power Plant in the United Kingdom

    Business Wire
  • Rolls-Royce shares surge as SMR unit bags multi-billion pound Swedish nuclear contract

    Energy
    Rendering of a small modular reactor (SMR) design showcasing compact and efficient nuclear energy solution
  • Reeves to protect energy and infrastructure projects from court challenges

    Legal
    Rachel Reeves speaking at an IOD event.
  • Type One Energy Appoints Bernard Looney to Board of Directors

    Business Wire
  • From Cutting-Edge Research to Industry: Focused Energy Plans Spin-Off of Sourcelight

    Business Wire
  • The City is paying the price for Britain’s energy failure

    Opinion
    UK energy power lines spanning a rural landscape, highlighting infrastructure and sustainability efforts in the energy sec...
  • Vattenfall energy portfolio poised to be snapped up by private equity firm

    Merger/Acquisition
    Brent Cross Town aerial view showcasing urban development and green spaces from the official website

CityAM Canada — business, markets and opinion for Canadian readers.

Sections

  • Business
  • Markets
  • Tech
  • AI
  • Economics
  • Opinion
  • Cities

Company

  • About
  • Contact

Legal

  • Terms of Use
  • Privacy Policy
  • Cookie Policy
© 2026 CityAM Canada. All rights reserved.
Terms · Privacy · Cookies