      Kia Oval worth £80m to the UK economy as Test gets underway

      Cityscape at dusk showcasing skyline with prominent skyscrapers under a vibrant sky, ideal for business news context.

      Submit a story

      Tell us your story.

      Submit
  • Opinion
  • Sport
    • Latest Sports News
      • Sport
      • Sport Business
    • From our partners
      • The Morning Briefing: SBS x CityAM
      • Aramco Team Series
      • LIV Golf
    • Featured

      Kia Oval worth £80m to the UK economy as Test gets underway

      Cityscape at dusk showcasing skyline with prominent skyscrapers under a vibrant sky, ideal for business news context.

      Submit a story

      Tell us your story.

      Submit
  • Life&Style
    • Life&Style
      • Life&Style
      • Toast the City Awards
      • The Magazine
      • Travel
      • Culture
      • Motoring
      • Wellness
      • The RED BULLETiN
      • Do it with Shared Ownership
      • Media Speak Hub
    • Featured

      Old Pulteney releases 50-year-old whisky for 200th anniversary

      Old Pulteney 50-Year-Old single malt Scotch whisky bottle with elegant packaging on display, highlighting luxury and craft...

      Submit a story

      Tell us your story.

      Submit
  • Investec
  • Events
  • Latest Paper
Wednesday 24 January 2018 11:48 am

Mapped: Here’s how the Elizabeth Line will open in stages as the Crossrail project wraps up

By: Rebecca Smith

Add as a preferred source on Google

In December, Transport for London (TfL) revealed its updated Tube map for the Elizabeth Line once the Crossrail project wraps up.

But with phasing of the project occurring until the full line is open, certain parts will be in operation at various times before the full railway is in action in December 2019.

So, TfL has provided some handy maps to show what will be running at each stage of the process, after the first milestone saw the first Elizabeth Line train enter passenger service between the Liverpool Street main line and Shenfield in June.

Read more: Crossrail facing "increasing cost and schedule pressures"

Elizabeth Line timeline
  • Stage one: Trains start operating from Liverpool Street to Shenfield – June 2017 (TfL Rail)
  • Stage two: Trains start operating from Heathrow to Paddington (main line platforms) – May 2018 (TfL Rail)
  • Stage three: Trains start operating from Paddington (Elizabeth line platforms) to Abbey Wood, through the new central tunnels – December 2018
  • Stage four: Trains start operating from Paddington (Elizabeth line platforms) to Shenfield – May 2019
  • Stage five: Full through service (including Elizabeth line services to Reading) – December 2019

(Click or tap for full-sized versions.)

Stage 2 May 2018: New class 345 rolling stock introduced on TfL Rail services Paddington – Heathrow

Stage 3 December 2018: Elizabeth Line opens with services running Liverpool Street – Shenfield; Paddington – Heathrow; Paddington – Abbey Wood

Stage 4 May 2019: Elizabeth Line through services extend to Shenfield

Stage 5 December 2019: Elizabeth Line fully open with services running between Reading and Heathrow and Abbey Wood and Shenfield


(Source: TfL)

And here's how it will look among the rest of the network:


(Source: TfL)

TfL says the £14.8bn project is on track to be delivered on time and within budget, though London's transport commissioner has said it faces "increasing cost and schedule pressures".

Issues have included Whitechapel station works being completed later than budgeted, as well as delayed works at Woolwich station.

The next big milestone of TfL Rail services starting between Paddington and Heathrow in May is also under pressure due to troubles with train software.

The railway is set to open from December 2018 in phases, and will then be known as the Elizabeth Line when the central tunnels under London are open.

Read more: Crossrail's coming: Iconic roundels unveiled on Elizabeth Line stations

 

Share this article

  • Facebook
  • X
  • LinkedIn
  • WhatsApp
  • Email

Similarly tagged content:

Sections

  • News

Categories

  • Business
  • Transport & Infrastructure

Trending Articles

  • Rathbones to suspend thousands of client account inflows after FCA probe deals £530m blow

  • More Big Four blues as Deloitte plans to slash UK audit roles

  • Rolls-Royce shares surge as SMR unit bags multi-billion pound Swedish nuclear contract

  • As it happened: FTSE 100 relief rally runs out of steam as BP and Shell weigh; Oil hits three-month low

  • London Tech Week sums up everything wrong with UK tech

More from CityAM

  • Chaos at Heathrow as burst water pipe causes train cancellations

    Travel
    Heathrow and several European airports are suffering from a cyber attack.
  • TfL decommissions Oxford Circus air conditioning despite sweltering heat

    Transport & Infrastructure
    Nationwide found that 60 per cent of Londoners use trains or the Tube every week.
  • Why are so many people abandoning sex toys on the Tube?

    Opinion
    Abandoned doll on London Tube seat holding CityAM newspaper, capturing urban life and public transport atmosphere
  • New HS2 budget to blow £33bn hole in public finances

    Transport & Infrastructure
    HS2 construction worker inspecting tunnel progress, showcasing infrastructure development and engineering expertise
  • Plans for 25,000-capacity NBA basketball arena called London Colosseum

    Sport Business
    Interior of Londons Colosseum Arena set up for a boxing event, featuring a large ring and tiered seating under bright lights
  • Fideres Study Finds TfL Fare Zones Disproportionately Burden Ethnic Minority Commuters

    Business Wire
  • Upgrading the grid risks ending up like HS2

    Opinion
    Electricity grid infrastructure with high-voltage power lines and pylons under a clear sky, representing energy distribution.
  • ‘Obscene’ – HS2 on track to cost at least £102bn as minister slams ‘gold-plated folly’

    Transport & Infrastructure
    HS2 construction progress at Birmingham station with cranes and workers, highlighting UKs high-speed rail project development

CityAM Canada — business, markets and opinion for Canadian readers.

Sections

  • Business
  • Markets
  • Tech
  • AI
  • Economics
  • Opinion
  • Cities

Company

  • About
  • Contact

Legal

  • Terms of Use
  • Privacy Policy
  • Cookie Policy
© 2026 CityAM Canada. All rights reserved.
Terms · Privacy · Cookies